Project C-238: Scott Elementary School

Current Board Adopted Budget:

$18,890,060


School Scott Elementary School
3300 Russell
Houston, Texas 77026
Phone 713-671-4110
Fax 713-671-4114
Consolidation

Current Phase
Construction Phase
Progress: 15%


Feeder Wheatley High School
District District II - Rhonda Skillern-Jones
CMPA N/A
Manager Elena Stephens
Contractor Cadence McShane Construction
Architect ESPA Corp.
Project Status

Foundation is in place and erection of the steel structural frame has begun.

Target Year Open/Complete: Q2/2013

Description
Building 750 Student Elementary School Replacement (Consolidation of Scott and Dogan Elementary Schools on the Dogan Campus).


Last Updated: 8/20/2012